๐ Fish Processing Unit: Custom Timeline & Task List
Phase 1: Planning & Land Setup (Weeks 1–4)
✅ Week 1–2
-
Identify and acquire industrial-zoned land or premises
-
Conduct feasibility study: capacity, target market (domestic/export), financials
-
Prepare layout & architectural plans (with designated processing, storage, packaging, waste zones)
✅ Week 3–4
-
Submit building & factory layout for local authority + Chief Inspector of Factories approval (if applicable)
-
Apply for power connection and water supply
-
Get fire safety plan vetted by Fire Department
Phase 2: Core Registrations & Licenses (Weeks 4–8)
✅ Week 4–5
-
Apply for FSSAI Food Business License (online at foscos.fssai.gov.in)
-
Register under Shops & Establishment Act / Trade License with local body
-
Apply for Consent to Establish from State Pollution Control Board (SPCB)
-
Apply for Factory License (if ≥10 workers with power or ≥20 without)
✅ Week 6–8
-
If planning export:
→ Register with Marine Products Export Development Authority (MPEDA)
→ Apply for EIA/EIC approvals if exporting to EU, USA -
If using cold storage: Apply for Cold Storage License
-
Register under Legal Metrology Act for packaging & labeling compliance
Phase 3: Construction & Equipment Setup (Weeks 8–16)
✅ Week 8–12
-
Begin civil construction + install drainage, flooring, cold rooms, processing lines
-
Install effluent treatment plant (ETP), ensure SPCB standards
-
Procure machinery: filleting, freezing, IQF (Individual Quick Freezing), packaging lines
✅ Week 12–16
-
Set up electricals, safety systems, backup generators
-
Hire and train workforce on safety & hygiene standards
-
Conduct fire safety inspection + get Fire Department NOC
Phase 4: Final Approvals & Testing (Weeks 16–20)
✅ Week 16–18
-
Apply for Consent to Operate (SPCB) after completing setup
-
Conduct internal trials of equipment, cold chain, product lines
-
Implement hygiene protocols: sanitation, pest control, PPE for workers
✅ Week 18–20
-
Submit water/effluent/air test results to SPCB
-
Conduct food safety testing (microbiological, chemical) through NABL-accredited labs
-
Set up product traceability system (batch coding, supplier records)
Phase 5: Operations Launch (Weeks 20–24)
✅ Week 20–22
-
Finalize supplier contracts for raw material (fish catch, farms)
-
Arrange logistics: cold storage, refrigerated trucks, distributors/exporters
-
Conduct HACCP system check (if exporting)
✅ Week 22–24
-
Launch production on small scale (pilot batch)
-
Submit sample export batches for clearance (if applicable)
-
Start full-scale operations & marketing
๐ Ongoing (Post Launch)
✅ Regular renewal of licenses (FSSAI, SPCB, Factory License)
✅ Maintain registers for labor, safety, and quality control
✅ Schedule annual audits (internal + third-party, if exporting)
✅ Continuously monitor environmental compliance (SPCB submissions)
๐ง Who Should Do What?
Task Group | Responsibility |
---|---|
Licenses & Permits | Owner/Operations Manager + Legal Consultant |
Factory Setup & Equipment | Project Manager + Engineering Team |
Workforce Hiring & Training | HR Manager + Production Supervisor |
Food Safety & Quality Setup | Quality Manager + FSSAI Consultant |
Export Compliance | Export Manager + MPEDA Liaison |
Environmental Compliance | ETP Consultant + SPCB Liaison |