Tuesday, August 25, 2026

APPLICATION TO AMEND THE WRITTEN VERSION ON BEHALF OF THE OPPOSITE PARTY NO. 1

 

BEFORE THE HON’BLE WEST BENGAL STATE CONSUMER DISPUTES REDRESSAL COMMISSION, KOLKATA

Kreta Suraksha Bhawan
11A, Mirza Ghalib Street,
Kolkata – 700087

 

I.A. No. __________ of 2026

IN

CONSUMER COMPLAINT NO. CC/894/2019

NEW CASE NO. SC/19/CC/894/2019

 

IN THE MATTER OF:

Smt. Molina Dutta

...Complainant

-Versus-

 

Sri Sujit Saha & Others

...Opposite Parties

 

APPLICATION TO AMEND THE WRITTEN VERSION

ON BEHALF OF THE OPPOSITE PARTY NO. 1

 

MOST RESPECTFULLY SHEWETH;

 

1.   That the above-mentioned Consumer Complaint is pending before this Hon’ble Commission and the answering Opposite Party No. 1, namely Sri Sujit Saha, is contesting the said proceeding from the very inception.

 

2.   That the answering Opposite Party No. 1 had already filed his Written Version wherein the allegations, averments and claims made by the Complainant were specifically denied and the maintainability of the complaint, absence of deficiency in service and the circumstances responsible for the alleged delay were specifically pleaded.

 

3.   That amongst other things, the answering Opposite Party No. 1 had specifically pleaded in the Written Version that the property in question was a joint property; that the Complainant along with the other co-sharers had entered into a Development Agreement with the answering Opposite Party No. 1; that a General Power of Attorney had also been executed; that the sanctioned plan had been obtained from the Kolkata Municipal Corporation; that construction was required to be undertaken subject to the property being free from legal impediments; that civil litigation concerning the property had intervened; and that there was no deficiency in service attributable to the answering Opposite Party No. 1.

 

4.   That the present application is being filed for the limited purpose of clarifying, elaborating, supplementing and bringing into proper chronological perspective the material facts already forming the foundation of the defence of the answering Opposite Party No. 1.

 

5.   That the proposed amendment does not seek to introduce a new or inconsistent defence, does not seek to withdraw any admission and does not alter the fundamental nature and character of the defence already taken in the Written Version.

 

6.   That the necessity of placing the aforesaid facts and circumstances before this Hon’ble Commission in greater detail has further arisen in view of the Questionnaire served by the Complainant upon the answering Opposite Party No. 1. The answering Opposite Party No. 1 had duly prepared and submitted his reply to the said Questionnaire; however, the same could not be filed within the time stipulated by this Hon’ble Commission owing to a bona fide and unavoidable communication gap between the answering Opposite Party No. 1 and his learned Advocate. The delay was neither intentional nor deliberate, nor was it occasioned with any object of prolonging the proceeding or causing prejudice to the Complainant. Nevertheless, as the said reply was submitted at a belated stage, this Hon’ble Commission was pleased to debar the answering Opposite Party No. 1 from filing the same, and consequently, the said reply was not taken on record. The answering Opposite Party No. 1 most respectfully submits that the relevant facts are material for the proper and effective adjudication of the real controversy between the parties and are, therefore, being stated in detail in the present pleading, subject always to the orders of this Hon’ble Commission.

 

7.   That in the aforesaid Reply/Affidavit prepared in answer to the Questionnaire served by the Complainant, the answering Opposite Party No. 1 had truthfully disclosed on oath all material facts and particulars relating to the transaction forming the subject matter of the present consumer complaint. Such disclosures, inter alia, concerned the execution, terms and effect of the Development Agreement entered into between the parties; the preparation, submission and sanction of the building plan by the competent municipal or statutory authority; the institution and pendency of the connected civil litigation; the passing and operation of the order directing maintenance of status quo; and the consequent legal and practical restrictions affecting the progress and completion of the construction work during the relevant period.

 

8.   The answering Opposite Party No. 1 had further disclosed the subsequent completion of the construction, the steps taken for making the subject property or allotted portion ready for delivery, the offer made to the Complainant to take possession thereof, and the Complainant’s refusal, neglect and/or failure to accept such possession and complete the necessary formalities. The said facts are directly relevant to determining whether there was any actual deficiency in service or unfair trade practice on the part of the answering Opposite Party No. 1 and whether the alleged delay was attributable to him. The answering Opposite Party No. 1 submits that the delay, if any, occurred because of circumstances beyond his control, including the pending civil proceedings and the subsisting order of status quo, and not because of any wilful omission, negligence or deliberate default on his part.

 

9.   It is further submitted that the aforesaid statements were not invented subsequently or introduced merely to fill up any alleged lacuna in the defence. They constitute an integral part of the consistent case of the answering Opposite Party No. 1 and are supported by the relevant agreements, sanctioned plan, judicial orders, correspondence and other contemporaneous records. Although the Reply/Affidavit to the Questionnaire was not taken on record on account of the procedural delay, the material facts stated therein remain necessary for a complete, fair and effective adjudication of the dispute and for preventing any miscarriage of justice.

 

10.               That the proposed amendment is therefore intended to bring the defence in the Written Version in conformity with and to properly consolidate the material facts already disclosed by the answering Opposite Party No. 1 in the present proceeding.

 

11.               That the facts sought to be incorporated through the proposed amendment are supported by contemporaneous records, including the Development Agreement, sanctioned building plan, pleadings and orders passed in the connected civil proceeding, records relating to the progress and completion of construction, communications offering possession and other relevant documents. The proposed amendment is, therefore, founded upon existing and verifiable records and does not introduce any fabricated, speculative or inconsistent defence.

 

12.               That the proposed amendment does not change the fundamental nature and character of the defence already disclosed in the Written Version. The consistent defence of the answering Opposite Party No. 1 has always been that he did not commit any wilful default or deficiency in service; that the progress of construction was affected by legal proceedings and the order of status quo; that the construction was subsequently completed; and that possession was offered but was not accepted by the Complainant. The amendment merely provides the necessary particulars and a more comprehensive explanation of the facts;

 

(a)  That the Complainant, along with the other co-sharers/landowners, had entered into a Development Agreement dated 21.12.2012 with the answering Opposite Party No. 1 for development and construction of the building at premises being D/82, Bapuji Nagar, P.O. Regent Estate, Police Station – Jadavpur, Kolkata – 700092, under Ward No. 96 of the Kolkata Municipal Corporation, District South 24 Parganas.

 

(b) That the said Development Agreement was duly registered in the Office of the learned District Sub-Registrar-I, Alipore, South 24 Parganas, in Book No. I, being Registration No. 4460 for the year 2012.

 

(c)  That on the same date, namely 21.12.2012, the Complainant and the other co-sharers executed a General Power of Attorney in favour of the answering Opposite Party No. 1 for taking necessary steps in connection with the development and construction of the subject property.

 

(d) That, significantly, Point/Clause No. 8 of the said General Power of Attorney authorized the attorney to appoint solicitors, advocates, pleaders and other legal representatives and to execute necessary Vakalatnamas, warrants, applications and other documents.

 

(e)  That Point/Clause No. 9 of the said General Power of Attorney further authorized the answering Opposite Party No. 1 to commence, prosecute, defend and conduct suits, actions, applications, references and other proceedings before Courts and competent authorities and to sign, verify and affirm pleadings, applications and other documents as may be necessary.

 

(f)   That the aforesaid authority was conferred upon the answering Opposite Party No. 1 in order to enable him to deal with legal and procedural impediments which might arise in the course of the development and construction of the property and to facilitate smooth completion of the project.

 

(g)  That the answering Opposite Party No. 1 obtained the sanctioned building plan from the Kolkata Municipal Corporation in June 2013, and construction was contemplated to be completed within a period of 18 (eighteen) months, subject to the property remaining free from legal impediments and encumbrances and subject to the terms of the Development Agreement.

 

(h) That thereafter a civil dispute concerning the subject property arose and Title Suit No. 391 of 2014 was instituted before the learned Civil Judge (Junior Division), 1st Court at Alipore, South 24 Parganas, concerning premises D/82, Bapuji Nagar Colony, Police Station – Jadavpur, Kolkata – 700092.

 

(i)   That in the said Title Suit, an order of status quo was passed on 01.09.2014 by the learned Civil Judge (Junior Division), 1st Court at Alipore.

 

(j)   That subsequently, by Order No. 09 dated 03.12.2014, the landowners/co-sharers, including the Complainant and the answering Opposite Party No. 1, were added as defendants in the said Title Suit.

 

(k) That the said civil proceedings and the order of status quo constituted a substantial legal impediment to the development and construction of the property.

 

(l)   That the answering Opposite Party No. 1 could not lawfully proceed with construction in disregard of an order of status quo passed by a competent Civil Court.

 

(m)                That the Complainant was herself fully aware of the aforesaid litigation and was a party to the proceedings and, therefore, cannot now contend that the period consumed by the said litigation was attributable to any wilful or deliberate default on the part of the answering Opposite Party No. 1.

 

(n) That the other co-sharers/landowners were also concerned with and affected by the said civil litigation and the answering Opposite Party No. 1 had no control over the time consumed in adjudication of the said dispute.

 

(o)  That the said civil litigation ultimately came to an end and upon removal of the legal impediment, the answering Opposite Party No. 1 proceeded with the construction work.

 

(p) That the construction of the building was ultimately completed and the respective portions/share of the owners were made available to the respective co-sharers/landowners.

 

(q)  That the other co-sharers/landowners, including Amritalal Dutta, Dhananjoy Dutta, Ajay Dutta, Digbijay Dutta and Smt. Gopa Dutta, accepted possession of their respective portions.

 

(r)  That the answering Opposite Party No. 1 also offered possession of the respective owner's allocation to the Complainant.

 

(s)  That a Letter of Possession was sent to the Complainant through post and the same was duly received by her.

 

(t)   That notwithstanding the completion of construction and offer of possession, the Complainant refused and/or failed to accept possession of her respective allocation and instead continued with the present Consumer Complaint alleging delay and deficiency in service.

 

13.               That the aforesaid facts are material and necessary for determining whether the alleged delay, if any, was attributable to the answering Opposite Party No. 1 or whether such delay was occasioned by circumstances beyond his control.

 

14.               That the aforesaid facts are also necessary for determining whether, after completion of construction and offer of possession, any continuing deficiency in service can legally be attributed to the answering Opposite Party No. 1 merely because the Complainant did not accept possession.

 

15.               That in the aforesaid circumstances, the answering Opposite Party No. 1 seeks leave to incorporate the following paragraphs in the Written Version after the existing pleadings relating to the Development Agreement and the circumstances causing delay, the following;

 

SCHEDULE FOR AMENDMENT

After paragraph 19;

 

19(a) “That the Complainant, along with the other co-sharers/landowners, had entered into a duly registered Development Agreement dated 21.12.2012 with the answering Opposite Party No. 1 for development and construction of the premises being D/82, Bapuji Nagar, P.O. Regent Estate, Police Station – Jadavpur, Kolkata – 700092, under Ward No. 96 of the Kolkata Municipal Corporation.”

 

19(b) “That on the same date, namely 21.12.2012, the Complainant and the other co-sharers executed a General Power of Attorney in favour of the answering Opposite Party No. 1 authorising him, inter alia, to take necessary legal and procedural steps and to conduct proceedings before Courts and competent authorities in connection with the development and construction of the property.”

 

19(c) “That the answering Opposite Party No. 1 obtained the sanctioned building plan from the Kolkata Municipal Corporation in June 2013 and the construction was contemplated to be completed within a period of 18 months, subject to the property remaining free from legal impediments and encumbrances.”

 

19(d) “That thereafter Title Suit No. 391 of 2014 was instituted concerning the subject property and an order of status quo was passed on 01.09.2014 by the learned Civil Judge (Junior Division), 1st Court at Alipore. Subsequently, by Order No. 09 dated 03.12.2014, the landowners/co-sharers including the Complainant and the answering Opposite Party No. 1 were added as defendants in the said suit.”

 

19(e) “That the aforesaid civil litigation and order of status quo constituted a legal impediment to the construction and development work and the answering Opposite Party No. 1 could not lawfully proceed with construction in violation of the order of the competent Civil Court.”

 

19(f) “That the Complainant herself was fully aware of and was a party to the aforesaid litigation and the answering Opposite Party No. 1 had no control whatsoever over the period consumed in the adjudication of the said civil dispute.”

 

19(g) “That after the civil litigation came to an end and the legal impediment was removed, the answering Opposite Party No. 1 proceeded with the construction and ultimately completed the building.”

 

19(h) “That the respective portions of the owners were thereafter made available and handed over to the respective co-sharers/landowners, including the other co-sharers, who accepted possession of their respective portions.”

 

19(i) “That the answering Opposite Party No. 1 also offered possession of the respective owner's allocation to the Complainant and sent a Letter of Possession to her through post, which was duly received by the Complainant.”

 

19(j) “That despite completion of construction and offer of possession, the Complainant refused and/or failed to accept possession and has continued the present Consumer Complaint alleging delay and deficiency in service.”

 

19(k) “That in the aforesaid facts and circumstances, no deficiency in service can be attributed to the answering Opposite Party No. 1 and the period consumed by the civil litigation and order of status quo cannot be treated as wilful or deliberate delay on the part of the answering Opposite Party No. 1.”

 

19(l) “That the answering Opposite Party No. 1 craves leave to rely upon the Development Agreement dated 21.12.2012, General Power of Attorney dated 21.12.2012, sanctioned building plan, plaint and orders passed in Title Suit No. 391 of 2014, Letter of Possession, postal receipt, postal tracking report and other documents already on record.”

 

19(m) “Photostat copy of the said Letter of Possession along with Postal receipt and the Postal Track Report, are annexed herewith and marked as Annexure – “A”.”

 

19(n) “Photostat copy of the Orders and Plaint of the Title Suit no. 391 of 2014, are annexed herewith and marked as Annexure – “B”.”

 

19(o) “The O.P. no. 1, agreed to compensate while any delay occurred at his behest; But case in hand apparently shows the cause of delay if any has been duly occurred at the behest of the consumer complainant and her other co-sharers, by way of Litigation being Title Suit no. 391 of 2014, therefore the O.P. no. 1, is well supposed to get such compensation from the consumer complainant.

 

Sl. No.

Date

Particulars’

01

21-12-2012

Development Agreement;

02

June’ 2013

Sanctioned Building Plan;

03

December’ 2014

Period of 18 months;

04

01-09-2014

Title Suit no. 391 of 2014 instituted and status quo granted over the property;

05

June’ 2017

Title Suit no. 391 of 2014 disposed off;

06

June’ 2017

Period of 18 months encumbered by a period of another 2 years 7 months, up-till June’ 2017;

07

October’ 2017

Building Completed and Possession handed over to the Owners; save and except the present Consumer Complainant, as she refused to take the Letter of Possession.

 

16.               That the present Consumer Complaint was instituted under the Consumer Protection Act, 1986, and the answering Opposite Party No. 1 respectfully submits that the present application is being made in furtherance of the principles of natural justice and the procedural discretion of this Hon’ble Commission to ensure complete and effective adjudication of the consumer dispute.

 

17.               That Section 13(4) of the Consumer Protection Act, 1986 conferred upon the Consumer Forum, for the purposes of adjudicating a consumer dispute, certain powers analogous to those exercised by a Civil Court, including receiving evidence and requiring production of documents, subject to the statutory framework.

 

18.               That the proposed amendment is necessary for determining the real controversy between the parties, namely whether there was deficiency in service or delay attributable to the answering Opposite Party No. 1.

 

19.               That the proposed amendment also does not seek to withdraw any admission made by the answering Opposite Party No. 1.

 

20.               That the proposed amendment does not change the fundamental nature of the defence that there was no deficiency in service attributable to the answering Opposite Party No. 1.

 

21.               That the proposed amendment merely provides the necessary factual particulars and chronological sequence explaining the circumstances already pleaded in the Written Version.

 

22.               That the answering Opposite Party No. 1 is conscious that the present proceeding has reached the stage of final hearing/final argument and has, therefore, approached this Hon’ble Commission with utmost bona fides.

23.               That the answering Opposite Party No. 1 respectfully submits that the present application is not intended to reopen the evidence already concluded.

 

24.               That the answering Opposite Party No. 1 is not seeking to introduce a new factual foundation which would require commencement of a fresh trial.

 

25.               That the amendment merely sets out the material particulars necessary to enable this Hon’ble Commission to properly appreciate the aforesaid defence.

 

26.               That the Complainant was herself a co-sharer/landowner and was aware of the civil litigation concerning the subject property and therefore cannot claim surprise in respect of the facts concerning Title Suit No. 391 of 2014.

 

27.               That no irreparable prejudice shall be caused to the Complainant by permitting the amendment.

 

28.               That without prejudice, if this Hon’ble Commission considers it necessary to grant the Complainant an opportunity to respond to the amended portions, the answering Opposite Party No. 1 has no objection to the same.

 

29.               That in K.K. Constructions v. Mohammad Yakub Khan, 2025 SCC OnLine NCDRC 443, the Hon’ble National Consumer Disputes Redressal Commission considered a belated amendment at the stage of final hearing and recognized that the advanced stage of the proceeding is not by itself an absolute prohibition against amendment where the amendment is relevant to adjudication and appropriate safeguards can be adopted to protect the other side.

 

30.               That the present case stands on a stronger footing because the proposed amendment is directly connected with the existing defence and the material facts have already been disclosed by the answering Opposite Party No. 1 in the present proceedings.

 

31.               That the amendment is therefore necessary to enable this Hon’ble Commission to determine the real controversy upon consideration of the complete factual background.

 

32.               That the present application has been made bona fide and in the interest of justice.

 

In the premises aforesaid, the Opposite Party No. 1 most respectfully prays that Your Lordship/Lordships may graciously be pleased to;

 

a) Allow the present application;

 

b) Grant leave to the Opposite Party No. 1 to amend, the Written Version already filed in the present Consumer Complaint in terms of the proposed Schedule for amendments stated herein;

 

c) Direct that the amended Written Version shall be treated as part and parcel of the Written Version already on record;

 

d) Pass such further and/or other order or orders as this Hon’ble Commission may deem fit and proper in the facts and circumstances of the case.

 

And for this act of kindness, the Opposite Party No. 1 as in duty bound shall ever pray.

 

SCHEDULE FOR AMENDMENT

After paragraph 19;

 

19(a) “That the Complainant, along with the other co-sharers/landowners, had entered into a duly registered Development Agreement dated 21.12.2012 with the answering Opposite Party No. 1 for development and construction of the premises being D/82, Bapuji Nagar, P.O. Regent Estate, Police Station – Jadavpur, Kolkata – 700092, under Ward No. 96 of the Kolkata Municipal Corporation.”

 

19(b) “That on the same date, namely 21.12.2012, the Complainant and the other co-sharers executed a General Power of Attorney in favour of the answering Opposite Party No. 1 authorising him, inter alia, to take necessary legal and procedural steps and to conduct proceedings before Courts and competent authorities in connection with the development and construction of the property.”

 

19(c) “That the answering Opposite Party No. 1 obtained the sanctioned building plan from the Kolkata Municipal Corporation in June 2013 and the construction was contemplated to be completed within a period of 18 months, subject to the property remaining free from legal impediments and encumbrances.”

 

19(d) “That thereafter Title Suit No. 391 of 2014 was instituted concerning the subject property and an order of status quo was passed on 01.09.2014 by the learned Civil Judge (Junior Division), 1st Court at Alipore. Subsequently, by Order No. 09 dated 03.12.2014, the landowners/co-sharers including the Complainant and the answering Opposite Party No. 1 were added as defendants in the said suit.”

 

19(e) “That the aforesaid civil litigation and order of status quo constituted a legal impediment to the construction and development work and the answering Opposite Party No. 1 could not lawfully proceed with construction in violation of the order of the competent Civil Court.”

 

19(f) “That the Complainant herself was fully aware of and was a party to the aforesaid litigation and the answering Opposite Party No. 1 had no control whatsoever over the period consumed in the adjudication of the said civil dispute.”

 

19(g) “That after the civil litigation came to an end and the legal impediment was removed, the answering Opposite Party No. 1 proceeded with the construction and ultimately completed the building.”

 

19(h) “That the respective portions of the owners were thereafter made available and handed over to the respective co-sharers/landowners, including the other co-sharers, who accepted possession of their respective portions.”

 

19(i) “That the answering Opposite Party No. 1 also offered possession of the respective owner's allocation to the Complainant and sent a Letter of Possession to her through post, which was duly received by the Complainant.”

 

19(j) “That despite completion of construction and offer of possession, the Complainant refused and/or failed to accept possession and has continued the present Consumer Complaint alleging delay and deficiency in service.”

 

19(k) “That in the aforesaid facts and circumstances, no deficiency in service can be attributed to the answering Opposite Party No. 1 and the period consumed by the civil litigation and order of status quo cannot be treated as wilful or deliberate delay on the part of the answering Opposite Party No. 1.”

 

19(l) “That the answering Opposite Party No. 1 craves leave to rely upon the Development Agreement dated 21.12.2012, General Power of Attorney dated 21.12.2012, sanctioned building plan, plaint and orders passed in Title Suit No. 391 of 2014, Letter of Possession, postal receipt, postal tracking report and other documents already on record.”

 

19(m) “Photostat copy of the said Letter of Possession along with Postal receipt and the Postal Track Report, are annexed herewith and marked as Annexure – “A”.”

 

19(n) “Photostat copy of the Orders and Plaint of the Title Suit no. 391 of 2014, are annexed herewith and marked as Annexure – “B”.”

 

19(o) “The O.P. no. 1, agreed to compensate while any delay occurred at his behest; But case in hand apparently shows the cause of delay if any has been duly occurred at the behest of the consumer complainant and her other co-sharers, by way of Litigation being Title Suit no. 391 of 2014, therefore the O.P. no. 1, is well supposed to get such compensation from the consumer complainant.

 

Sl. No.

Date

Particulars’

01

21-12-2012

Development Agreement;

02

June’ 2013

Sanctioned Building Plan;

03

December’ 2014

Period of 18 months;

04

01-09-2014

Title Suit no. 391 of 2014 instituted and status quo granted over the property;

05

June’ 2017

Title Suit no. 391 of 2014 disposed off;

06

June’ 2017

Period of 18 months encumbered by a period of another 2 years 7 months, up-till June’ 2017;

07

October’ 2017

Building Completed and Possession handed over to the Owners; save and except the present Consumer Complainant, as she refused to take the Letter of Possession.

 

====================XXXX======================

AFFIDAVIT

 

I, Sujit Saha, son of Late Sambhu Nath Saha, aged about 52 years, by faith Hindu, by occupation Business, residing at Premises No. A/61/2, Bapuji Nagar, Kolkata – 700092, do hereby solemnly affirm and state as follows;

 

  1. That I am the Opposite Party No. 1 in the above Consumer Complaint and am well acquainted with the facts and circumstances of the case and competent to swear this affidavit.

 

  1. That the statements made in paragraphs 1 to 15 of the said application are based upon the records of the case and my personal knowledge and are true and correct.

 

  1. That the statements made in paragraphs 16 to 32 contain legal submissions based upon legal advice received and believed by me to be true and correct.

 

  1. That the proposed amendment is necessary for complete and effective adjudication of the real controversy between the parties.

 

  1. That the contents of the present affidavit are true and correct to my knowledge and belief and nothing material has been concealed therefrom.

 

 

 

DEPONENT

Identified by me,

 

Advocate

 

 

 

NOTARY

 

No comments:

Post a Comment